Nashville · Antioch / Barnes Road Last checked Nov 16, 2026, 3:25 PM CT

Elam Station Construction Tracker

The 187-home Elam Station development behind 6520 Sunnywood Dr, and the Sunnywood Drive extension through the site. This page is updated weekly.

No construction yet.

The rezoning is final, but no final site plan, plat, or grading permit has been filed. The developer's plan estimates construction from December 2027 to December 2029, and the plan does not say which phase builds the Sunnywood segment.

Rezoned
Stage
Effective Nov 13, 2026
1 of 10
Approvals done
Only the rezoning so far
0
Permits issued
Grading, site, or building
Dec 2027
Planned start
Developer's estimate on the plan

What has to happen before ground breaks

StepStatusNotes
Rezoning (SP preliminary plan) 2026SP-018-001 Approved Ordinance BL2026-1558, effective Nov 13, 2026
Corrected preliminary SP plan Not filed Due before or with the final site plan
Final site plan (2026SP-018-002) Not filed Must include grading, landscaping, architecture (at least 15% glazing on street facades), and the Sunnywood traffic-calming design worked out with NDOT. Often approved by Planning staff on the Commission's behalf and listed in the Director's Report
Water and sewer construction plans and capacity fees Not approved Capacity permits T2025099814 and T2025099822 exist; plans and fees are needed before final site plan approval
Stormwater final review Not approved May include a stream and wetland determination
NDOT public road construction drawings Not approved Covers the Sunnywood extension; may include a street lighting plan
Final plat Not filed May be required before permits. Recorded with the Davidson County Register of Deeds; lots can't be sold until it is
Metro Water grading permit, then pre-construction meeting None Required to disturb over 10,000 sq ft. Metro Water holds a pre-construction meeting before any earth moves. This is the last gate before digging. No permits of any kind for the parcel in Metro's permit data
Building permits (Codes) None Come after grading; Fire Marshal access and water supply must be met first
TDEC state stormwater permit (notice of coverage) Unknown Needed to disturb an acre or more; TDEC search couldn't be reached

The project

Elam Station, case 2026SP-018-001

109 multi-family units and 78 single-family lots on 55.6 acres at 1065 Barnes Rd (Map 173 Parcel 076). Phase 1 has 27 homes, Phase 2 has 51, and Phase 3 has the 109 multi-family units. Building starts on the southern end.

The Sunnywood extension

Sunnywood continues from 6520 Sunnywood Dr through the site as a collector street with bike lanes. The plan sheet labels it "Sunnywood Drive (60' ROW)" along the site's southern edge; the city street plan lists 59 ft. It's been on Metro's street plan since at least 2017. Conditions require traffic calming on the street extensions, designed with NDOT.

Other street changes

Boddington Ln extends to a cul-de-sac, Turfway Ln extends east to a stub-out for a future connection, Sweetberry Dr extends to a cul-de-sac with a walking path, and there's a connection to Brockman Ln. NDOT also requires a left-turn lane at the Barnes Rd entrance and 31 ft of right-of-way along Barnes Rd.

Layout

Single-family lots 1 to 78 are on the southern side next to Sugar Valley. The 109 multi-family units sit on Lot 79 (23.5 acres) on the Barnes Rd side, on a private road. Short-term rentals are banned.

Expiration

The rezoning doesn't expire. If there's no development activity within 4 years of Nov 13, 2026, the Planning Commission may review it, and no grading or building permits can be issued during that review.

Separate 2022 Barnes Rd plan

Case 2022SP-065-001, north of Barnes Rd, approved Feb 2023. No final site plan, plat, or permits found since. Its plan describes a collector that would eventually link Sunnywood to Bell Rd.

Developer and engineer

Green Trails, LLC (Rick Deckbar, 615-397-4513). The engineer is Land Solutions Company (Jennifer Speich, jennifer@landsolutionsco.net).

Timeline

DateEvent
Mar 9, 2026Application accepted; planner Savannah Garland assigned
Mar 19 to Aug 6, 2026Agency reviews: Fire Marshal approved as submitted (Mar 19), Metro Water approved with conditions (Mar 24), Stormwater approved with conditions (Apr 14), Planning required corrections (Jul 6), NDOT approved with conditions (Aug 6)
Jul 23, 2026Planning Commission deferred to Aug 13 (8-0), no hearing held
Aug 13, 2026Planning Commission approved 7-0 with conditions (RS2026-155)
Sep 1, 2026Council first reading
Oct 6, 2026Council public hearing and second reading
Nov 5, 2026Council third reading passed, 32 yes votes. Companion bill BL2026-1559 (building materials) traveled with it
Nov 6, 2026Mayor approved
Nov 13, 2026Rezoning took effect
Nov 16, 2026Tracking started: weekly check, plus Metro Planning and District 31 emails

Weekly checks

Every Monday the city's case tracker, Planning Commission agendas, Metro permit records, and TDEC stormwater filings are checked. Metro Planning and District 31 emails are checked as they arrive.

CheckedResult
Nov 16, 2026Baseline. No final site plan, plat, or permits filed.

How you'll know construction is starting

A final site plan case appears

2026SP-018-002 shows up in the Development Tracker or on a Planning Commission agenda.

Signs on site

A posted TDEC notice of coverage, silt fence, and a gravel construction entrance.